ZIP boundary report
Permit processing times in ZIP 60610
Across 3,503 issued permits assigned to ZIP 60610, the median processing time was 4 days.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Permit processing times in ZIP 60610, 3,503 issued permit records show a median processing time of 4 days; 75% were issued within 25 days and 90% within 66 days, covering January 2021 through September 15, 2026.
The median was 5 days slower than the previous 12 months.
Permit processing times in ZIP 60610: wait distribution
For Permit processing times in ZIP 60610, 3,503 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Permit processing times in ZIP 60610: annual permit timing
Permit processing times in ZIP 60610 has 6 publishable issue-year cohorts spanning 2021–2026, representing 3,503 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 598 | 0 days | 11 days | 57 days |
| 2022 | 711 | 0 days | 11 days | 51 days |
| 2023 | 606 | 1 day | 13 days | 56 days |
| 2024 | 572 | 11 days | 34 days | 70 days |
| 2025 | 600 | 11 days | 27 days | 64 days |
| 2026* | 416 | 14 days | 38 days | 87 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Permit processing times in ZIP 60610: ZIP codes with similar overall timing
Permit processing times in ZIP 60610 has 3,503 issued records, a 4 days median, and a 25 days 75th-percentile wait in this release.
More Permit processing times in ZIP 60610 comparisons
The Permit processing times in ZIP 60610 cohort contains 3,503 issued records; related links retain separate location and permit-category cohorts.
Express Permit Program 4 daysRenovation & Alteration 25 daysEasy Permit Process 0 daysSigns 34 daysElevator Equipment 0 daysNew Construction 6 daysScaffolding 0 daysWrecking & Demolition 43 days