ZIP code × permit type
Renovation & Alteration permits in ZIP 60610
The median renovation & alteration permit wait in ZIP 60610 was 25 days, based on 563 issued records.
Records checked5632021–Sep. 15, 2026
The short answer
Typical wait25 daysmedian issued permit
Usually within68 days75% of records
Long-wait edge137 days90% of records
Evidence563issued permits
The median was 8 days slower than the previous 12 months.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 101 | 0 days | 47 days | 92 days |
| 2022 | 122 | 0 days | 30 days | 97 days |
| 2023 | 100 | 22 days | 57 days | 105 days |
| 2024 | 97 | 46 days | 91 days | 149 days |
| 2025 | 77 | 41 days | 80 days | 136 days |
| 2026* | 66 | 50 days | 108 days | 183 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context