Renovation & Alteration permits in ZIP 60656
The median renovation & alteration permit wait in ZIP 60656 was 24 days, based on 132 issued records.
Records checked1322021–Sep. 15, 2026
The short answer
Typical wait24 daysmedian issued permit
Usually within68 days75% of records
Long-wait edge137 days90% of records
Evidence132issued permits
Not enough records for a year-over-year comparison.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 29 | 0 days | 30 days | 94 days |
| 2022 | 27 | 0 days | 14 days | 65 days |
| 2023 | 25 | 44 days | 99 days | 276 days |
| 2024 | 19 | 30 days | 51 days | 77 days |
| 2025 | 21 | 69 days | 121 days | 140 days |
| 2026* | 11 | 64 days | 110 days | 167 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.