Renovation & Alteration permits in ZIP 60613
The median renovation & alteration permit wait in ZIP 60613 was 28 days, based on 662 issued records.
Records checked6622021–Sep. 15, 2026
The short answer
Typical wait28 daysmedian issued permit
Usually within73 days75% of records
Long-wait edge152 days90% of records
Evidence662issued permits
The median was 14 days slower than the previous 12 months.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 116 | 3 days | 43 days | 102 days |
| 2022 | 118 | 2 days | 26 days | 93 days |
| 2023 | 119 | 37 days | 82 days | 157 days |
| 2024 | 132 | 32 days | 74 days | 162 days |
| 2025 | 104 | 48 days | 94 days | 158 days |
| 2026* | 73 | 62 days | 129 days | 220 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.