Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Citywide permit type

Renovation & Alteration processing times

Across Chicago, 36,906 issued renovation & alteration permits had a median processing time of 28 days.

Records checked36,9062021–Sep. 15, 2026

The short answer

Typical wait28 daysmedian issued permit
Usually within85 days75% of records
Long-wait edge169 days90% of records
Evidence36,906issued permits

The median was 8 days slower than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
23.1%
1–7 days
13.2%
8–30 days
15.4%
31–90 days
24.9%
91+ days
23.4%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
20217,2902 days50 days119 days
20227,7302 days53 days134 days
20236,40424 days84 days174 days
20246,17043 days98 days194 days
20255,48353 days109 days201 days
2026*3,82959 days123 days209 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

All permit types, from shortest to longest median

ReportMedian75% withinRecords
Easy Permit Process0 days1 day33,486
Elevator Equipment0 days0 days6,546
Reinstated Permit0 days0 days1,775
Scaffolding0 days0 days1,019
Wrecking & Demolition0 days55 days4,023
Express Permit Program1 day8 days91,329
Signs23 days61 days13,362
New Construction27 days92 days8,073
Renovation & Alteration28 days85 days36,906