Citywide permit type
Renovation & Alteration processing times
Across Chicago, 36,906 issued renovation & alteration permits had a median processing time of 28 days.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Renovation & Alteration processing times, 36,906 issued permit records show a median processing time of 28 days; 75% were issued within 85 days and 90% within 169 days, covering January 2021 through September 15, 2026.
The median was 8 days slower than the previous 12 months.
Renovation & Alteration processing times: wait distribution
For Renovation & Alteration processing times, 36,906 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Renovation & Alteration processing times: annual permit timing
Renovation & Alteration processing times has 6 publishable issue-year cohorts spanning 2021–2026, representing 36,906 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 7,290 | 2 days | 50 days | 119 days |
| 2022 | 7,730 | 2 days | 53 days | 134 days |
| 2023 | 6,404 | 24 days | 84 days | 174 days |
| 2024 | 6,170 | 43 days | 98 days | 194 days |
| 2025 | 5,483 | 53 days | 109 days | 201 days |
| 2026* | 3,829 | 59 days | 123 days | 209 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Renovation & Alteration processing times: All permit types, from shortest to longest median
Renovation & Alteration processing times has 36,906 issued records, a 28 days median, and a 85 days 75th-percentile wait in this release.
| Report | Median | 75% within | Records |
|---|---|---|---|
| Easy Permit Process | 0 days | 1 day | 33,486 |
| Elevator Equipment | 0 days | 0 days | 6,546 |
| Reinstated Permit | 0 days | 0 days | 1,775 |
| Scaffolding | 0 days | 0 days | 1,019 |
| Wrecking & Demolition | 0 days | 55 days | 4,023 |
| Express Permit Program | 1 day | 8 days | 91,329 |
| Signs | 23 days | 61 days | 13,362 |
| New Construction | 27 days | 92 days | 8,073 |
| Renovation & Alteration | 28 days | 85 days | 36,906 |
More Renovation & Alteration processing times comparisons
The Renovation & Alteration processing times cohort contains 36,906 issued records; related links retain separate location and permit-category cohorts.
Loop Area detailNear North Side Area detailNear West Side Area detailWest Town Area detailLake View Area detailLincoln Park Area detailAustin Area detailLogan Square Area detailPortage Park Area detailIrving Park Area detailAuburn Gresham Area detailNorth Center Area detail