Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

Renovation & Alteration permits in Near North Side

The typical renovation & alteration permit issued in Near North Side took 13 days. The 75th-percentile wait was 50 days.

Records checked2,5862021–Sep. 15, 2026

The short answer

Typical wait13 daysmedian issued permit
Usually within50 days75% of records
Long-wait edge104 days90% of records
Evidence2,586issued permits

The median was 3 days slower than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
33.1%
1–7 days
11.8%
8–30 days
18.4%
31–90 days
23.9%
91+ days
12.8%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
20214540 days26 days93 days
20225210 days25 days76 days
20234474 days48 days95 days
202441732 days65 days121 days
202543326 days58 days108 days
2026*31431 days70 days146 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Renovation & Alteration timing in comparable community areas

ReportMedian75% withinRecords
Near North Side13 days50 days2,586
Burnside8.5 days67 days28
Near West Side8 days52 days2,042
Fuller Park20 days98 days68
Hyde Park20 days60 days448
Ohare6 days39 days304
East Side21 days71 days96
Oakland22 days131 days85