Official community area
Near North Side permit processing times
For 14,726 issued permits in Near North Side, the median processing time was 4 days; 75% were issued within 20 days.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Near North Side permit processing times, 14,726 issued permit records show a median processing time of 4 days; 75% were issued within 20 days and 90% within 59 days, covering January 2021 through September 15, 2026.
The median was 1 day slower than the previous 12 months.
Near North Side permit processing times: wait distribution
For Near North Side permit processing times, 14,726 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Near North Side permit processing times: annual permit timing
Near North Side permit processing times has 6 publishable issue-year cohorts spanning 2021–2026, representing 14,726 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 2,552 | 0 days | 12 days | 50 days |
| 2022 | 2,728 | 0 days | 13 days | 51 days |
| 2023 | 2,685 | 1 day | 18 days | 65 days |
| 2024 | 2,594 | 8 days | 28 days | 68 days |
| 2025 | 2,474 | 6 days | 21 days | 52 days |
| 2026* | 1,693 | 7 days | 25 days | 75 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Near North Side permit processing times: Nearby points in the citywide timing distribution
Near North Side permit processing times has 14,726 issued records, a 4 days median, and a 20 days 75th-percentile wait in this release.
| Report | Median | 75% within | Records |
|---|---|---|---|
| Near North Side | 4 days | 20 days | 14,726 |
| West Town | 4 days | 32 days | 7,607 |
| East Garfield Park | 3 days | 28 days | 1,600 |
| Grand Boulevard | 3 days | 34 days | 1,871 |
| Lincoln Park | 3 days | 28 days | 6,764 |
| North Park | 3 days | 18 days | 1,222 |
| Uptown | 3 days | 21 days | 2,727 |
| Woodlawn | 3 days | 27 days | 2,225 |
More Near North Side permit processing times comparisons
The Near North Side permit processing times cohort contains 14,726 issued records; related links retain separate location and permit-category cohorts.
Express Permit Program 3 daysRenovation & Alteration 13 daysSigns 32 daysEasy Permit Process 0 daysElevator Equipment 0 daysNew Construction 7 daysScaffolding 0 daysReinstated Permit 0 daysWrecking & Demolition 50 days