Grand Boulevard permit processing times
For 1,871 issued permits in Grand Boulevard, the median processing time was 3 days; 75% were issued within 34 days.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Grand Boulevard permit processing times, 1,871 issued permit records show a median processing time of 3 days; 75% were issued within 34 days and 90% within 114 days, covering January 2021 through September 15, 2026.
The median was 8 days faster than the previous 12 months.
Grand Boulevard permit processing times: wait distribution
For Grand Boulevard permit processing times, 1,871 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Grand Boulevard permit processing times: annual permit timing
Grand Boulevard permit processing times has 6 publishable issue-year cohorts spanning 2021–2026, representing 1,871 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 389 | 0 days | 21 days | 86 days |
| 2022 | 384 | 0 days | 13 days | 127 days |
| 2023 | 281 | 0 days | 35 days | 152 days |
| 2024 | 299 | 11 days | 39 days | 92 days |
| 2025 | 296 | 13 days | 55 days | 124 days |
| 2026* | 222 | 7 days | 42 days | 112 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Grand Boulevard permit processing times: Nearby points in the citywide timing distribution
Grand Boulevard permit processing times has 1,871 issued records, a 3 days median, and a 34 days 75th-percentile wait in this release.
| Report | Median | 75% within | Records |
|---|---|---|---|
| East Garfield Park | 3 days | 28 days | 1,600 |
| Grand Boulevard | 3 days | 34 days | 1,871 |
| Lincoln Park | 3 days | 28 days | 6,764 |
| North Park | 3 days | 18 days | 1,222 |
| Uptown | 3 days | 21 days | 2,727 |
| Woodlawn | 3 days | 27 days | 2,225 |
| Douglas | 2.5 days | 21 days | 992 |
| Avondale | 2 days | 21 days | 2,361 |
More Grand Boulevard permit processing times comparisons
The Grand Boulevard permit processing times cohort contains 1,871 issued records; related links retain separate location and permit-category cohorts.
Express Permit Program 2 daysRenovation & Alteration 29 daysEasy Permit Process 0 daysNew Construction 57 daysSigns 46 daysReinstated Permit 0 daysElevator Equipment 0 days