Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Official community area

Grand Boulevard permit processing times

For 1,871 issued permits in Grand Boulevard, the median processing time was 3 days; 75% were issued within 34 days.

Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026

Records checked1,8712021–Sep. 15, 2026

The short answer

For Grand Boulevard permit processing times, 1,871 issued permit records show a median processing time of 3 days; 75% were issued within 34 days and 90% within 114 days, covering January 2021 through September 15, 2026.

Typical wait3 daysmedian issued permit
Usually within34 days75% of records
Long-wait edge114 days90% of records
Evidence1,871issued permits

The median was 8 days faster than the previous 12 months.

Grand Boulevard permit processing times: wait distribution

For Grand Boulevard permit processing times, 1,871 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.

Same day
39.1%
1–7 days
19.5%
8–30 days
15.4%
31–90 days
13.7%
91+ days
12.3%

Change over time

Grand Boulevard permit processing times: annual permit timing

Grand Boulevard permit processing times has 6 publishable issue-year cohorts spanning 2021–2026, representing 1,871 issued records in the annual table.

Issue yearRecordsMedian75th percentile90th percentile
20213890 days21 days86 days
20223840 days13 days127 days
20232810 days35 days152 days
202429911 days39 days92 days
202529613 days55 days124 days
2026*2227 days42 days112 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Grand Boulevard permit processing times: Nearby points in the citywide timing distribution

Grand Boulevard permit processing times has 1,871 issued records, a 3 days median, and a 34 days 75th-percentile wait in this release.

ReportMedian75% withinRecords
East Garfield Park3 days28 days1,600
Grand Boulevard3 days34 days1,871
Lincoln Park3 days28 days6,764
North Park3 days18 days1,222
Uptown3 days21 days2,727
Woodlawn3 days27 days2,225
Douglas2.5 days21 days992
Avondale2 days21 days2,361