Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

Renovation & Alteration permits in Grand Boulevard

The typical renovation & alteration permit issued in Grand Boulevard took 29 days. The 75th-percentile wait was 106 days.

Records checked4002021–Sep. 15, 2026

The short answer

Typical wait29 daysmedian issued permit
Usually within106 days75% of records
Long-wait edge217 days90% of records
Evidence400issued permits

The median was 65 days slower than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
16.5%
1–7 days
17.0%
8–30 days
17.2%
31–90 days
21.5%
91+ days
27.8%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
2021865.5 days63 days142 days
2022967.5 days86 days190 days
20236934 days134 days379 days
20246544 days92 days228 days
20255844 days118 days200 days
2026*26120 days193 days348 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Renovation & Alteration timing in comparable community areas

ReportMedian75% withinRecords
Grand Boulevard29 days106 days400
Auburn Gresham28 days96 days612
Avondale28 days85 days534
Lake View28 days77 days1,391
Rogers Park28 days80 days375
Edgewater31 days83 days638
West Garfield Park32 days91 days360
Greater Grand Crossing32 days95 days596