Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

Renovation & Alteration permits in Avondale

The typical renovation & alteration permit issued in Avondale took 28 days. The 75th-percentile wait was 85 days.

Records checked5342021–Sep. 15, 2026

The short answer

Typical wait28 daysmedian issued permit
Usually within85 days75% of records
Long-wait edge183 days90% of records
Evidence534issued permits

The median was 25 days slower than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
23.0%
1–7 days
13.1%
8–30 days
16.1%
31–90 days
24.2%
91+ days
23.6%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
20211242 days35 days94 days
20221166 days55 days151 days
20239020 days73 days178 days
20248950 days118 days231 days
20256758 days122 days218 days
2026*4862 days171 days277 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Renovation & Alteration timing in comparable community areas

ReportMedian75% withinRecords
Auburn Gresham28 days96 days612
Avondale28 days85 days534
Lake View28 days77 days1,391
Rogers Park28 days80 days375
Grand Boulevard29 days106 days400
Chatham26 days77 days444
Armour Square25 days76 days153
Edgewater31 days83 days638