Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

Renovation & Alteration permits in Auburn Gresham

The typical renovation & alteration permit issued in Auburn Gresham took 28 days. The 75th-percentile wait was 96 days.

Records checked6122021–Sep. 15, 2026

The short answer

Typical wait28 daysmedian issued permit
Usually within96 days75% of records
Long-wait edge183 days90% of records
Evidence612issued permits

The median was 22 days slower than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
19.0%
1–7 days
16.5%
8–30 days
16.2%
31–90 days
22.4%
91+ days
26.0%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
20211414 days40 days110 days
20221303 days62 days143 days
202311323 days102 days255 days
20248250 days114 days214 days
20256468 days118 days173 days
2026*8286 days141 days200 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Renovation & Alteration timing in comparable community areas

ReportMedian75% withinRecords
Auburn Gresham28 days96 days612
Avondale28 days85 days534
Lake View28 days77 days1,391
Rogers Park28 days80 days375
Grand Boulevard29 days106 days400
Chatham26 days77 days444
Armour Square25 days76 days153
Edgewater31 days83 days638