Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Citywide report

Chicago permit processing times

Across 196,519 issued permits since 2021, the citywide median was 1 day. The range changes sharply by permit type and location.

Records checked196,5192021–Sep. 15, 2026

The short answer

Typical wait1 daymedian issued permit
Usually within17 days75% of records
Long-wait edge71 days90% of records
Evidence196,519issued permits

The median was unchanged from the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
44.0%
1–7 days
21.0%
8–30 days
16.5%
31–90 days
10.7%
91+ days
7.8%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
202138,4440 days8 days55 days
202237,6560 days8 days53 days
202333,7080 days13 days72 days
202432,9235 days26 days77 days
202531,7066 days26 days82 days
2026*22,0826 days29 days90 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Community areas with the shortest overall medians

ReportMedian75% withinRecords
Armour Square0 days17 days755
Avalon Park0 days11 days1,045
Calumet Heights0 days9 days1,129
Chicago Lawn0 days12 days2,383
Dunning0 days9 days1,934
East Side0 days8 days823
Edison Park0 days18 days735
Forest Glen0 days17 days1,297
Hegewisch0 days5 days700
Jefferson Park0 days13 days1,489