Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Citywide permit type

Express Permit Program processing times

Across Chicago, 91,329 issued express permit program permits had a median processing time of 1 day.

Records checked91,3292021–Sep. 15, 2026

The short answer

Typical wait1 daymedian issued permit
Usually within8 days75% of records
Long-wait edge25 days90% of records
Evidence91,329issued permits

The median was unchanged from the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
44.7%
1–7 days
29.8%
8–30 days
17.8%
31–90 days
5.9%
91+ days
1.8%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
202112,4750 days3 days22 days
202211,5310 days4 days31 days
202311,9380 days8 days37 days
202421,0352 days9 days25 days
202520,1863 days9 days21 days
2026*14,1642 days9 days20 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

All permit types, from shortest to longest median

ReportMedian75% withinRecords
Easy Permit Process0 days1 day33,486
Elevator Equipment0 days0 days6,546
Reinstated Permit0 days0 days1,775
Scaffolding0 days0 days1,019
Wrecking & Demolition0 days55 days4,023
Express Permit Program1 day8 days91,329
Signs23 days61 days13,362
New Construction27 days92 days8,073
Renovation & Alteration28 days85 days36,906