The typical express permit program permit issued in Logan Square took 1 day. The 75th-percentile wait was 8 days.

Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026

Records checked1,7652021–Sep. 15, 2026

The short answer

For Express Permit Program permits in Logan Square, 1,765 issued permit records show a median processing time of 1 day; 75% were issued within 8 days and 90% within 26 days, covering January 2021 through September 15, 2026.

Typical wait1 daymedian issued permit
Usually within8 days75% of records
Long-wait edge26 days90% of records
Evidence1,765issued permits

The median was unchanged from the previous 12 months.

Express Permit Program permits in Logan Square: wait distribution

For Express Permit Program permits in Logan Square, 1,765 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.

Same day
41.6%
1–7 days
32.7%
8–30 days
18.0%
31–90 days
6.1%
91+ days
1.6%

Change over time

Express Permit Program permits in Logan Square: annual permit timing

Express Permit Program permits in Logan Square has 6 publishable issue-year cohorts spanning 2021–2026, representing 1,765 issued records in the annual table.

Issue yearRecordsMedian75th percentile90th percentile
20211850 days3 days9.6 days
20221610 days3 days22 days
20231830 days3 days26 days
20244642 days9 days28 days
20254422.5 days12 days33 days
2026*3303 days11 days21 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Express Permit Program permits in Logan Square: Express Permit Program timing in comparable community areas

Express Permit Program permits in Logan Square has 1,765 issued records, a 1 day median, and a 8 days 75th-percentile wait in this release.

ReportMedian75% withinRecords
Albany Park1 day6 days997
Auburn Gresham1 day7 days1,679
Austin1 day7 days2,565
Avondale1 day6 days866
Beverly1 day7 days843
Brighton Park1 day9 days684
Burnside1 day5 days127
Chatham1 day7 days1,207