Community area × permit type

Express Permit Program permits in Avondale

The typical express permit program permit issued in Avondale took 1 day. The 75th-percentile wait was 6 days.

Records checked8662021–Sep. 15, 2026

The short answer

Typical wait1 daymedian issued permit
Usually within6 days75% of records
Long-wait edge19 days90% of records
Evidence866issued permits

The median was unchanged from the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
47.0%
1–7 days
30.8%
8–30 days
15.7%
31–90 days
4.8%
91+ days
1.6%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
20211360 days1 day20 days
20221130 days1 day20 days
20231180 days3.8 days16 days
20242062 days7 days17 days
20251662 days11 days19 days
2026*1273 days12 days23 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Express Permit Program timing in comparable community areas

ReportMedian75% withinRecords
Albany Park1 day6 days997
Auburn Gresham1 day7 days1,679
Austin1 day7 days2,565
Avondale1 day6 days866
Beverly1 day7 days843
Brighton Park1 day9 days684
Burnside1 day5 days127
Chatham1 day7 days1,207