Chicago Lawn permit processing times

For 2,383 issued permits in Chicago Lawn, the median processing time was 0 days; 75% were issued within 12 days.

Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026

Records checked2,3832021–Sep. 15, 2026

The short answer

For Chicago Lawn permit processing times, 2,383 issued permit records show a median processing time of 0 days; 75% were issued within 12 days and 90% within 53 days, covering January 2021 through September 15, 2026.

Typical wait0 daysmedian issued permit
Usually within12 days75% of records
Long-wait edge53 days90% of records
Evidence2,383issued permits

The median was 3 days faster than the previous 12 months.

Chicago Lawn permit processing times: wait distribution

For Chicago Lawn permit processing times, 2,383 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.

Same day
51.0%
1–7 days
18.0%
8–30 days
17.2%
31–90 days
7.4%
91+ days
6.5%

Change over time

Chicago Lawn permit processing times: annual permit timing

Chicago Lawn permit processing times has 6 publishable issue-year cohorts spanning 2021–2026, representing 2,383 issued records in the annual table.

Issue yearRecordsMedian75th percentile90th percentile
20215120 days6 days33 days
20224820 days3.8 days21 days
20233380 days10 days37 days
20244395 days19 days63 days
20253895 days27 days95 days
2026*2233 days15 days42 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Chicago Lawn permit processing times: Nearby points in the citywide timing distribution

Chicago Lawn permit processing times has 2,383 issued records, a 0 days median, and a 12 days 75th-percentile wait in this release.

ReportMedian75% withinRecords
Armour Square0 days17 days755
Avalon Park0 days11 days1,045
Calumet Heights0 days9 days1,129
Chicago Lawn0 days12 days2,383
Dunning0 days9 days1,934
East Side0 days8 days823
Edison Park0 days18 days735
Forest Glen0 days17 days1,297