Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

Renovation & Alteration permits in Chicago Lawn

The typical renovation & alteration permit issued in Chicago Lawn took 43 days. The 75th-percentile wait was 112 days.

Records checked3562021–Sep. 15, 2026

The short answer

Typical wait43 daysmedian issued permit
Usually within112 days75% of records
Long-wait edge220 days90% of records
Evidence356issued permits

The median was 17 days slower than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
15.7%
1–7 days
12.6%
8–30 days
14.3%
31–90 days
27.8%
91+ days
29.5%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
20217014 days65 days174 days
20227411 days76 days195 days
20235525 days112 days194 days
20247148 days94 days238 days
20256680 days192 days306 days
2026*2074 days129 days269 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Renovation & Alteration timing in comparable community areas

ReportMedian75% withinRecords
Chicago Lawn43 days112 days356
Dunning43 days109 days264
Edison Park43 days96 days155
West Ridge43 days106 days475
Hermosa44 days102 days182
New City44 days116 days526
Clearing44 days114 days107
Douglas44 days120 days157