Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

Renovation & Alteration permits in West Ridge

The typical renovation & alteration permit issued in West Ridge took 43 days. The 75th-percentile wait was 106 days.

Records checked4752021–Sep. 15, 2026

The short answer

Typical wait43 daysmedian issued permit
Usually within106 days75% of records
Long-wait edge200 days90% of records
Evidence475issued permits

The median was 41 days slower than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
16.4%
1–7 days
11.4%
8–30 days
13.9%
31–90 days
28.4%
91+ days
29.9%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
2021802 days56 days110 days
20229719 days83 days184 days
20239944 days115 days247 days
20248765 days134 days209 days
20256763 days108 days183 days
2026*4578 days174 days251 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Renovation & Alteration timing in comparable community areas

ReportMedian75% withinRecords
Chicago Lawn43 days112 days356
Dunning43 days109 days264
Edison Park43 days96 days155
West Ridge43 days106 days475
Hermosa44 days102 days182
New City44 days116 days526
Clearing44 days114 days107
Douglas44 days120 days157