Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Official community area

West Ridge permit processing times

For 2,695 issued permits in West Ridge, the median processing time was 2 days; 75% were issued within 17 days.

Records checked2,6952021–Sep. 15, 2026

The short answer

Typical wait2 daysmedian issued permit
Usually within17 days75% of records
Long-wait edge77 days90% of records
Evidence2,695issued permits

The median was 1 day slower than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
42.8%
1–7 days
21.2%
8–30 days
17.2%
31–90 days
10.2%
91+ days
8.6%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
20215370 days7 days43 days
20225140 days12 days76 days
20234680 days22 days101 days
20244697 days25 days87 days
20254006 days24 days64 days
2026*3075 days25 days100 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Nearby points in the citywide timing distribution

ReportMedian75% withinRecords
Avondale2 days21 days2,361
Bridgeport2 days24 days1,920
Brighton Park2 days19 days1,507
Englewood2 days24 days2,131
Lake View2 days23 days6,844
Logan Square2 days29 days5,067
Loop2 days15 days15,467
Lower West Side2 days31 days2,358