Official community area
Brighton Park permit processing times
For 1,507 issued permits in Brighton Park, the median processing time was 2 days; 75% were issued within 19 days.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Brighton Park permit processing times, 1,507 issued permit records show a median processing time of 2 days; 75% were issued within 19 days and 90% within 85 days, covering January 2021 through September 15, 2026.
The median was 4 days faster than the previous 12 months.
Brighton Park permit processing times: wait distribution
For Brighton Park permit processing times, 1,507 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Brighton Park permit processing times: annual permit timing
Brighton Park permit processing times has 6 publishable issue-year cohorts spanning 2021–2026, representing 1,507 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 339 | 0 days | 8 days | 58 days |
| 2022 | 263 | 0 days | 13 days | 89 days |
| 2023 | 236 | 2 days | 30 days | 110 days |
| 2024 | 241 | 5 days | 14 days | 66 days |
| 2025 | 265 | 12 days | 31 days | 87 days |
| 2026* | 163 | 6 days | 34 days | 100 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Brighton Park permit processing times: Nearby points in the citywide timing distribution
Brighton Park permit processing times has 1,507 issued records, a 2 days median, and a 19 days 75th-percentile wait in this release.
| Report | Median | 75% within | Records |
|---|---|---|---|
| Avondale | 2 days | 21 days | 2,361 |
| Bridgeport | 2 days | 24 days | 1,920 |
| Brighton Park | 2 days | 19 days | 1,507 |
| Englewood | 2 days | 24 days | 2,131 |
| Lake View | 2 days | 23 days | 6,844 |
| Logan Square | 2 days | 29 days | 5,067 |
| Loop | 2 days | 15 days | 15,467 |
| Lower West Side | 2 days | 31 days | 2,358 |
More Brighton Park permit processing times comparisons
The Brighton Park permit processing times cohort contains 1,507 issued records; related links retain separate location and permit-category cohorts.
Express Permit Program 1 dayEasy Permit Process 0 daysRenovation & Alteration 45 daysSigns 16 daysNew Construction 42 daysElevator Equipment 0 days