Community area × permit type
Signs permits in Brighton Park
The typical signs permit issued in Brighton Park took 16 days. The 75th-percentile wait was 39 days.
Records checked1442021–Sep. 15, 2026
The short answer
Typical wait16 daysmedian issued permit
Usually within39 days75% of records
Long-wait edge146 days90% of records
Evidence144issued permits
Not enough records for a year-over-year comparison.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 27 | 9 days | 81 days | 201 days |
| 2022 | 18 | 89 days | 134 days | 243 days |
| 2023 | 10 | 5 days | 22 days | 107 days |
| 2024 | 18 | 18 days | 127 days | 152 days |
| 2025 | 59 | 17 days | 22 days | 38 days |
| 2026* | 12 | 41 days | 50 days | 93 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Signs timing in comparable community areas
| Report | Median | 75% within | Records |
|---|---|---|---|
| Avondale | 16 days | 81 days | 276 |
| Brighton Park | 16 days | 39 days | 144 |
| Rogers Park | 16 days | 52 days | 173 |
| North Park | 16 days | 47 days | 120 |
| East Garfield Park | 17 days | 47 days | 42 |
| Pullman | 15 days | 110 days | 63 |
| South Deering | 15 days | 38 days | 83 |
| Auburn Gresham | 18 days | 37 days | 84 |