Signs permits in Pullman
The typical signs permit issued in Pullman took 15 days. The 75th-percentile wait was 110 days.
Records checked632021–Sep. 15, 2026
The short answer
Typical wait15 daysmedian issued permit
Usually within110 days75% of records
Long-wait edge125 days90% of records
Evidence63issued permits
Not enough records for a year-over-year comparison.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 19 | 6 days | 10 days | 13 days |
| 2025 | 19 | 124 days | 125 days | 125 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Signs timing in comparable community areas
| Report | Median | 75% within | Records |
|---|---|---|---|
| Pullman | 15 days | 110 days | 63 |
| South Deering | 15 days | 38 days | 83 |
| Clearing | 14 days | 19 days | 46 |
| North Park | 16 days | 47 days | 120 |
| Avondale | 16 days | 81 days | 276 |
| Belmont Cragin | 14 days | 33 days | 292 |
| Brighton Park | 16 days | 39 days | 144 |
| Gage Park | 14 days | 53 days | 115 |