Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

Signs permits in South Deering

The typical signs permit issued in South Deering took 15 days. The 75th-percentile wait was 38 days.

Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026

Records checked832021–Sep. 15, 2026

The short answer

For Signs permits in South Deering, 83 issued permit records show a median processing time of 15 days; 75% were issued within 38 days and 90% within 55 days, covering January 2021 through September 15, 2026.

Typical wait15 daysmedian issued permit
Usually within38 days75% of records
Long-wait edge55 days90% of records
Evidence83issued permits

Not enough records for a year-over-year comparison.

Signs permits in South Deering: wait distribution

For Signs permits in South Deering, 83 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.

Same day
0.0%
1–7 days
27.7%
8–30 days
36.1%
31–90 days
32.5%
91+ days
3.6%

Change over time

Signs permits in South Deering: annual permit timing

Signs permits in South Deering has 4 publishable issue-year cohorts spanning 2021–2025, representing 73 issued records in the annual table.

Issue yearRecordsMedian75th percentile90th percentile
2021279 days10 days11 days
2022146 days7 days54 days
20241643 days43 days58 days
20251638 days38 days38 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Signs permits in South Deering: Signs timing in comparable community areas

Signs permits in South Deering has 83 issued records, a 15 days median, and a 38 days 75th-percentile wait in this release.

ReportMedian75% withinRecords
Pullman15 days110 days63
South Deering15 days38 days83
Clearing14 days19 days46
North Park16 days47 days120
Avondale16 days81 days276
Belmont Cragin14 days33 days292
Brighton Park16 days39 days144
Gage Park14 days53 days115