Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Official community area

South Deering permit processing times

For 1,140 issued permits in South Deering, the median processing time was 0 days; 75% were issued within 8 days.

Records checked1,1402021–Sep. 15, 2026

The short answer

Typical wait0 daysmedian issued permit
Usually within8 days75% of records
Long-wait edge38 days90% of records
Evidence1,140issued permits

The median was 2 days faster than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
55.4%
1–7 days
18.7%
8–30 days
13.8%
31–90 days
7.4%
91+ days
4.7%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
20212680 days3 days33 days
20222220 days1.8 days33 days
20231860 days11 days46 days
20242051 day7 days39 days
20251536 days15 days38 days
2026*1064 days14 days36 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Nearby points in the citywide timing distribution

ReportMedian75% withinRecords
Armour Square0 days17 days755
Avalon Park0 days11 days1,045
Calumet Heights0 days9 days1,129
Chicago Lawn0 days12 days2,383
Dunning0 days9 days1,934
East Side0 days8 days823
Edison Park0 days18 days735
Forest Glen0 days17 days1,297