Community area × permit type
Renovation & Alteration permits in Edison Park
The typical renovation & alteration permit issued in Edison Park took 43 days. The 75th-percentile wait was 96 days.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Renovation & Alteration permits in Edison Park, 155 issued permit records show a median processing time of 43 days; 75% were issued within 96 days and 90% within 164 days, covering January 2021 through September 15, 2026.
Not enough records for a year-over-year comparison.
Renovation & Alteration permits in Edison Park: wait distribution
For Renovation & Alteration permits in Edison Park, 155 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Renovation & Alteration permits in Edison Park: annual permit timing
Renovation & Alteration permits in Edison Park has 6 publishable issue-year cohorts spanning 2021–2026, representing 155 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 30 | 9 days | 60 days | 139 days |
| 2022 | 39 | 1 day | 64 days | 135 days |
| 2023 | 23 | 37 days | 92 days | 146 days |
| 2024 | 30 | 50 days | 106 days | 195 days |
| 2025 | 17 | 73 days | 103 days | 142 days |
| 2026* | 16 | 70 days | 120 days | 296 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Renovation & Alteration permits in Edison Park: Renovation & Alteration timing in comparable community areas
Renovation & Alteration permits in Edison Park has 155 issued records, a 43 days median, and a 96 days 75th-percentile wait in this release.
| Report | Median | 75% within | Records |
|---|---|---|---|
| Chicago Lawn | 43 days | 112 days | 356 |
| Dunning | 43 days | 109 days | 264 |
| Edison Park | 43 days | 96 days | 155 |
| West Ridge | 43 days | 106 days | 475 |
| Hermosa | 44 days | 102 days | 182 |
| New City | 44 days | 116 days | 526 |
| Clearing | 44 days | 114 days | 107 |
| Douglas | 44 days | 120 days | 157 |
More Renovation & Alteration permits in Edison Park comparisons
The Renovation & Alteration permits in Edison Park cohort contains 155 issued records; related links retain separate location and permit-category cohorts.
All Edison Park permits Area reportRenovation & Alteration citywide Type report