Renovation & Alteration permits in Hermosa
The typical renovation & alteration permit issued in Hermosa took 44 days. The 75th-percentile wait was 102 days.
Records checked1822021–Sep. 15, 2026
The short answer
Typical wait44 daysmedian issued permit
Usually within102 days75% of records
Long-wait edge223 days90% of records
Evidence182issued permits
Not enough records for a year-over-year comparison.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 35 | 9 days | 64 days | 86 days |
| 2022 | 39 | 5 days | 64 days | 184 days |
| 2023 | 47 | 48 days | 103 days | 148 days |
| 2024 | 24 | 89 days | 203 days | 352 days |
| 2025 | 19 | 72 days | 148 days | 186 days |
| 2026* | 18 | 96 days | 212 days | 250 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Renovation & Alteration timing in comparable community areas
| Report | Median | 75% within | Records |
|---|---|---|---|
| Hermosa | 44 days | 102 days | 182 |
| New City | 44 days | 116 days | 526 |
| Chicago Lawn | 43 days | 112 days | 356 |
| Clearing | 44 days | 114 days | 107 |
| Douglas | 44 days | 120 days | 157 |
| Dunning | 43 days | 109 days | 264 |
| Edison Park | 43 days | 96 days | 155 |
| West Ridge | 43 days | 106 days | 475 |