Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

Renovation & Alteration permits in Armour Square

The typical renovation & alteration permit issued in Armour Square took 25 days. The 75th-percentile wait was 76 days.

Records checked1532021–Sep. 15, 2026

The short answer

Typical wait25 daysmedian issued permit
Usually within76 days75% of records
Long-wait edge164 days90% of records
Evidence153issued permits

Not enough records for a year-over-year comparison.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
28.8%
1–7 days
9.2%
8–30 days
15.7%
31–90 days
24.2%
91+ days
22.2%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
20214113 days67 days154 days
2022360 days45 days160 days
20232924 days76 days147 days
20242248 days92 days139 days
20251856 days96 days171 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Renovation & Alteration timing in comparable community areas

ReportMedian75% withinRecords
Armour Square25 days76 days153
Chatham26 days77 days444
Auburn Gresham28 days96 days612
Avondale28 days85 days534
Lake View28 days77 days1,391
Oakland22 days131 days85
Rogers Park28 days80 days375
East Side21 days71 days96