Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

Renovation & Alteration permits in Greater Grand Crossing

The typical renovation & alteration permit issued in Greater Grand Crossing took 32 days. The 75th-percentile wait was 95 days.

Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026

Records checked5962021–Sep. 15, 2026

The short answer

For Renovation & Alteration permits in Greater Grand Crossing, 596 issued permit records show a median processing time of 32 days; 75% were issued within 95 days and 90% within 194 days, covering January 2021 through September 15, 2026.

Typical wait32 daysmedian issued permit
Usually within95 days75% of records
Long-wait edge194 days90% of records
Evidence596issued permits

The median was 22 days slower than the previous 12 months.

Renovation & Alteration permits in Greater Grand Crossing: wait distribution

For Renovation & Alteration permits in Greater Grand Crossing, 596 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.

Same day
16.3%
1–7 days
18.3%
8–30 days
15.1%
31–90 days
24.2%
91+ days
26.2%

Change over time

Renovation & Alteration permits in Greater Grand Crossing: annual permit timing

Renovation & Alteration permits in Greater Grand Crossing has 6 publishable issue-year cohorts spanning 2021–2026, representing 596 issued records in the annual table.

Issue yearRecordsMedian75th percentile90th percentile
20211285 days47 days144 days
20221216 days64 days114 days
202312332 days89 days192 days
202410541 days134 days291 days
20256761 days102 days156 days
2026*5281 days146 days233 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Renovation & Alteration permits in Greater Grand Crossing: Renovation & Alteration timing in comparable community areas

Renovation & Alteration permits in Greater Grand Crossing has 596 issued records, a 32 days median, and a 95 days 75th-percentile wait in this release.

ReportMedian75% withinRecords
Greater Grand Crossing32 days95 days596
Irving Park32 days85 days707
South Shore32 days94 days711
West Garfield Park32 days91 days360
Albany Park33 days77 days422
Edgewater31 days83 days638
Lincoln Park33 days86 days1,340
Lincoln Square33 days82 days638