Community area × permit type
Renovation & Alteration permits in Albany Park
The typical renovation & alteration permit issued in Albany Park took 33 days. The 75th-percentile wait was 77 days.
Records checked4222021–Sep. 15, 2026
The short answer
Typical wait33 daysmedian issued permit
Usually within77 days75% of records
Long-wait edge153 days90% of records
Evidence422issued permits
The median was 11 days slower than the previous 12 months.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 79 | 4 days | 44 days | 77 days |
| 2022 | 98 | 2 days | 45 days | 142 days |
| 2023 | 74 | 30 days | 76 days | 150 days |
| 2024 | 74 | 52 days | 94 days | 143 days |
| 2025 | 54 | 54 days | 92 days | 191 days |
| 2026* | 43 | 68 days | 134 days | 200 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Renovation & Alteration timing in comparable community areas
| Report | Median | 75% within | Records |
|---|---|---|---|
| Albany Park | 33 days | 77 days | 422 |
| Lincoln Park | 33 days | 86 days | 1,340 |
| Lincoln Square | 33 days | 82 days | 638 |
| Mckinley Park | 33 days | 106 days | 176 |
| North Center | 33 days | 84 days | 755 |
| East Garfield Park | 34 days | 94 days | 400 |
| Greater Grand Crossing | 32 days | 95 days | 596 |
| Irving Park | 32 days | 85 days | 707 |