Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

Renovation & Alteration permits in Lincoln Park

The typical renovation & alteration permit issued in Lincoln Park took 33 days. The 75th-percentile wait was 86 days.

Records checked1,3402021–Sep. 15, 2026

The short answer

Typical wait33 daysmedian issued permit
Usually within86 days75% of records
Long-wait edge165 days90% of records
Evidence1,340issued permits

The median was 10 days slower than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
23.8%
1–7 days
8.3%
8–30 days
16.5%
31–90 days
27.8%
91+ days
23.6%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
20212845 days50 days111 days
20222620 days44 days142 days
202323534 days94 days181 days
202423648 days96 days174 days
202518459 days111 days195 days
2026*13969 days118 days211 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Renovation & Alteration timing in comparable community areas

ReportMedian75% withinRecords
Albany Park33 days77 days422
Lincoln Park33 days86 days1,340
Lincoln Square33 days82 days638
Mckinley Park33 days106 days176
North Center33 days84 days755
East Garfield Park34 days94 days400
Greater Grand Crossing32 days95 days596
Irving Park32 days85 days707