Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

Renovation & Alteration permits in Irving Park

The typical renovation & alteration permit issued in Irving Park took 32 days. The 75th-percentile wait was 85 days.

Records checked7072021–Sep. 15, 2026

The short answer

Typical wait32 daysmedian issued permit
Usually within85 days75% of records
Long-wait edge172 days90% of records
Evidence707issued permits

The median was 0.5 days slower than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
19.9%
1–7 days
15.7%
8–30 days
13.7%
31–90 days
27.7%
91+ days
22.9%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
20211432 days52 days97 days
20221493 days51 days151 days
202313119 days65 days140 days
202411152 days102 days222 days
202510563 days111 days178 days
2026*6860 days134 days250 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Renovation & Alteration timing in comparable community areas

ReportMedian75% withinRecords
Greater Grand Crossing32 days95 days596
Irving Park32 days85 days707
South Shore32 days94 days711
West Garfield Park32 days91 days360
Albany Park33 days77 days422
Edgewater31 days83 days638
Lincoln Park33 days86 days1,340
Lincoln Square33 days82 days638