Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

Renovation & Alteration permits in South Shore

The typical renovation & alteration permit issued in South Shore took 32 days. The 75th-percentile wait was 94 days.

Records checked7112021–Sep. 15, 2026

The short answer

Typical wait32 daysmedian issued permit
Usually within94 days75% of records
Long-wait edge185 days90% of records
Evidence711issued permits

The median was 40 days slower than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
14.2%
1–7 days
20.5%
8–30 days
14.8%
31–90 days
23.2%
91+ days
27.3%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
20211446 days62 days135 days
20221526 days71 days130 days
202313252 days154 days216 days
202414436 days95 days182 days
20259049 days101 days207 days
2026*4983 days133 days285 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Renovation & Alteration timing in comparable community areas

ReportMedian75% withinRecords
Greater Grand Crossing32 days95 days596
Irving Park32 days85 days707
South Shore32 days94 days711
West Garfield Park32 days91 days360
Albany Park33 days77 days422
Edgewater31 days83 days638
Lincoln Park33 days86 days1,340
Lincoln Square33 days82 days638