Official community area
South Shore permit processing times
For 2,918 issued permits in South Shore, the median processing time was 2 days; 75% were issued within 16 days.
Records checked2,9182021–Sep. 15, 2026
The short answer
Typical wait2 daysmedian issued permit
Usually within16 days75% of records
Long-wait edge78 days90% of records
Evidence2,918issued permits
The median was unchanged from the previous 12 months.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 563 | 0 days | 6 days | 58 days |
| 2022 | 567 | 0 days | 10 days | 63 days |
| 2023 | 492 | 0 days | 18 days | 123 days |
| 2024 | 528 | 6 days | 21 days | 88 days |
| 2025 | 466 | 6 days | 18 days | 68 days |
| 2026* | 302 | 6 days | 27 days | 89 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Nearby points in the citywide timing distribution
| Report | Median | 75% within | Records |
|---|---|---|---|
| Avondale | 2 days | 21 days | 2,361 |
| Bridgeport | 2 days | 24 days | 1,920 |
| Brighton Park | 2 days | 19 days | 1,507 |
| Englewood | 2 days | 24 days | 2,131 |
| Lake View | 2 days | 23 days | 6,844 |
| Logan Square | 2 days | 29 days | 5,067 |
| Loop | 2 days | 15 days | 15,467 |
| Lower West Side | 2 days | 31 days | 2,358 |