Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

New Construction permits in South Shore

The typical new construction permit issued in South Shore took 7.5 days. The 75th-percentile wait was 126 days.

Records checked302021–Sep. 15, 2026

The short answer

Typical wait7.5 daysmedian issued permit
Usually within126 days75% of records
Long-wait edge295 days90% of records
Evidence30issued permits

Not enough records for a year-over-year comparison.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
40.0%
1–7 days
10.0%
8–30 days
10.0%
31–90 days
6.7%
91+ days
33.3%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

New Construction timing in comparable community areas

ReportMedian75% withinRecords
South Shore7.5 days126 days30
Near North Side7 days48 days350
Oakland5 days114 days25
Lincoln Park12 days73 days406
Armour Square3 days70 days80
North Park2 days70 days39
Hyde Park1 day5.2 days120
Loop1 day7 days554