Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

New Construction permits in Armour Square

The typical new construction permit issued in Armour Square took 3 days. The 75th-percentile wait was 70 days.

Records checked802021–Sep. 15, 2026

The short answer

Typical wait3 daysmedian issued permit
Usually within70 days75% of records
Long-wait edge214 days90% of records
Evidence80issued permits

Not enough records for a year-over-year comparison.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
28.7%
1–7 days
30.0%
8–30 days
6.2%
31–90 days
13.8%
91+ days
21.2%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
2022170 days0 days69 days
2023113 days6 days9 days
2024167 days78 days220 days
2025101.5 days85 days118 days
2026*1741 days193 days406 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

New Construction timing in comparable community areas

ReportMedian75% withinRecords
Armour Square3 days70 days80
North Park2 days70 days39
Hyde Park1 day5.2 days120
Loop1 day7 days554
Near South Side1 day12 days251
Oakland5 days114 days25
Near North Side7 days48 days350
South Shore7.5 days126 days30