New Construction permits in Armour Square
The typical new construction permit issued in Armour Square took 3 days. The 75th-percentile wait was 70 days.
Records checked802021–Sep. 15, 2026
The short answer
Typical wait3 daysmedian issued permit
Usually within70 days75% of records
Long-wait edge214 days90% of records
Evidence80issued permits
Not enough records for a year-over-year comparison.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2022 | 17 | 0 days | 0 days | 69 days |
| 2023 | 11 | 3 days | 6 days | 9 days |
| 2024 | 16 | 7 days | 78 days | 220 days |
| 2025 | 10 | 1.5 days | 85 days | 118 days |
| 2026* | 17 | 41 days | 193 days | 406 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
New Construction timing in comparable community areas
| Report | Median | 75% within | Records |
|---|---|---|---|
| Armour Square | 3 days | 70 days | 80 |
| North Park | 2 days | 70 days | 39 |
| Hyde Park | 1 day | 5.2 days | 120 |
| Loop | 1 day | 7 days | 554 |
| Near South Side | 1 day | 12 days | 251 |
| Oakland | 5 days | 114 days | 25 |
| Near North Side | 7 days | 48 days | 350 |
| South Shore | 7.5 days | 126 days | 30 |