Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

New Construction permits in Near North Side

The typical new construction permit issued in Near North Side took 7 days. The 75th-percentile wait was 48 days.

Records checked3502021–Sep. 15, 2026

The short answer

Typical wait7 daysmedian issued permit
Usually within48 days75% of records
Long-wait edge142 days90% of records
Evidence350issued permits

The median was 14 days faster than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
28.0%
1–7 days
23.1%
8–30 days
16.0%
31–90 days
15.4%
91+ days
17.4%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
2021630 days20 days90 days
2022898 days40 days110 days
2023482 days39 days68 days
20245212 days128 days301 days
20255618 days58 days144 days
2026*425.5 days49 days180 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

New Construction timing in comparable community areas

ReportMedian75% withinRecords
Near North Side7 days48 days350
South Shore7.5 days126 days30
Oakland5 days114 days25
Armour Square3 days70 days80
Lincoln Park12 days73 days406
North Park2 days70 days39
Hyde Park1 day5.2 days120
Loop1 day7 days554