New Construction permits in Lincoln Park

The typical new construction permit issued in Lincoln Park took 12 days. The 75th-percentile wait was 73 days.

Records checked4062021–Sep. 15, 2026

The short answer

Typical wait12 daysmedian issued permit
Usually within73 days75% of records
Long-wait edge154 days90% of records
Evidence406issued permits

The median was 25 days faster than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
31.0%
1–7 days
16.0%
8–30 days
12.8%
31–90 days
21.2%
91+ days
19.0%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
2021810 days41 days120 days
2022730 days7 days61 days
2023548 days51 days175 days
20247652 days92 days150 days
20256734 days89 days172 days
2026*5526 days91 days156 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

New Construction timing in comparable community areas

ReportMedian75% withinRecords
Lincoln Park12 days73 days406
South Shore7.5 days126 days30
Near North Side7 days48 days350
Near West Side16 days74 days574
Lincoln Square16 days74 days206
Lake View18 days70 days470
Oakland5 days114 days25
Rogers Park18 days127 days34