Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

New Construction permits in Lincoln Square

The typical new construction permit issued in Lincoln Square took 16 days. The 75th-percentile wait was 74 days.

Records checked2062021–Sep. 15, 2026

The short answer

Typical wait16 daysmedian issued permit
Usually within74 days75% of records
Long-wait edge190 days90% of records
Evidence206issued permits

The median was 20 days slower than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
36.4%
1–7 days
10.2%
8–30 days
12.6%
31–90 days
19.9%
91+ days
20.9%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
2021460 days20 days52 days
2022460 days44 days166 days
2023230 days76 days117 days
20243151 days90 days229 days
20253751 days99 days273 days
2026*2350 days101 days190 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

New Construction timing in comparable community areas

ReportMedian75% withinRecords
Lincoln Square16 days74 days206
Near West Side16 days74 days574
Lake View18 days70 days470
Rogers Park18 days127 days34
Englewood22 days125 days28
Lincoln Park12 days73 days406
Douglas22 days103 days73
Uptown24 days122 days123