Community area × permit type
New Construction permits in Englewood
The typical new construction permit issued in Englewood took 22 days. The 75th-percentile wait was 125 days.
Records checked282021–Sep. 15, 2026
The short answer
Typical wait22 daysmedian issued permit
Usually within125 days75% of records
Long-wait edge230 days90% of records
Evidence28issued permits
Not enough records for a year-over-year comparison.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
New Construction timing in comparable community areas
| Report | Median | 75% within | Records |
|---|---|---|---|
| Englewood | 22 days | 125 days | 28 |
| Douglas | 22 days | 103 days | 73 |
| Uptown | 24 days | 122 days | 123 |
| Rogers Park | 18 days | 127 days | 34 |
| Lake View | 18 days | 70 days | 470 |
| West Pullman | 26 days | 69 days | 45 |
| Lincoln Square | 16 days | 74 days | 206 |
| Near West Side | 16 days | 74 days | 574 |