New Construction permits in Douglas

The typical new construction permit issued in Douglas took 22 days. The 75th-percentile wait was 103 days.

Records checked732021–Sep. 15, 2026

The short answer

Typical wait22 daysmedian issued permit
Usually within103 days75% of records
Long-wait edge153 days90% of records
Evidence73issued permits

Not enough records for a year-over-year comparison.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
32.9%
1–7 days
9.6%
8–30 days
8.2%
31–90 days
20.5%
91+ days
28.8%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
20211828 days114 days135 days
2022180 days35 days102 days
20251270 days87 days126 days
2026*10156 days207 days243 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

New Construction timing in comparable community areas

ReportMedian75% withinRecords
Douglas22 days103 days73
Englewood22 days125 days28
Uptown24 days122 days123
Rogers Park18 days127 days34
Lake View18 days70 days470
West Pullman26 days69 days45
Lincoln Square16 days74 days206
Near West Side16 days74 days574