Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

New Construction permits in Uptown

The typical new construction permit issued in Uptown took 24 days. The 75th-percentile wait was 122 days.

Records checked1232021–Sep. 15, 2026

The short answer

Typical wait24 daysmedian issued permit
Usually within122 days75% of records
Long-wait edge205 days90% of records
Evidence123issued permits

Not enough records for a year-over-year comparison.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
28.5%
1–7 days
9.8%
8–30 days
15.4%
31–90 days
16.3%
91+ days
30.1%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
2021260 days30 days122 days
2022358 days96 days219 days
20231821 days37 days69 days
20241455 days134 days232 days
20251466 days194 days526 days
2026*16120 days189 days254 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

New Construction timing in comparable community areas

ReportMedian75% withinRecords
Uptown24 days122 days123
Douglas22 days103 days73
West Pullman26 days69 days45
Englewood22 days125 days28
West Town28 days116 days508
Rogers Park18 days127 days34
Lake View18 days70 days470
Lincoln Square16 days74 days206