Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

New Construction permits in West Town

The typical new construction permit issued in West Town took 28 days. The 75th-percentile wait was 116 days.

Records checked5082021–Sep. 15, 2026

The short answer

Typical wait28 daysmedian issued permit
Usually within116 days75% of records
Long-wait edge246 days90% of records
Evidence508issued permits

The median was unchanged from the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
30.7%
1–7 days
8.1%
8–30 days
12.0%
31–90 days
19.3%
91+ days
29.9%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
20211060 days76 days152 days
20221140 days22 days176 days
20236933 days108 days246 days
202478106 days238 days286 days
20257254 days119 days242 days
2026*6970 days142 days224 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

New Construction timing in comparable community areas

ReportMedian75% withinRecords
West Town28 days116 days508
West Pullman26 days69 days45
Uptown24 days122 days123
Douglas22 days103 days73
Englewood22 days125 days28
Auburn Gresham36 days79 days29
Greater Grand Crossing36 days91 days36
Woodlawn37 days92 days257