Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

New Construction permits in Greater Grand Crossing

The typical new construction permit issued in Greater Grand Crossing took 36 days. The 75th-percentile wait was 91 days.

Records checked362021–Sep. 15, 2026

The short answer

Typical wait36 daysmedian issued permit
Usually within91 days75% of records
Long-wait edge108 days90% of records
Evidence36issued permits

Not enough records for a year-over-year comparison.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
33.3%
1–7 days
11.1%
8–30 days
5.6%
31–90 days
25.0%
91+ days
25.0%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

New Construction timing in comparable community areas

ReportMedian75% withinRecords
Auburn Gresham36 days79 days29
Greater Grand Crossing36 days91 days36
Woodlawn37 days92 days257
Edison Park38 days85 days37
North Center38 days84 days373
Ohare38 days116 days31
Brighton Park42 days86 days77
Logan Square42 days112 days310