Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

New Construction permits in Woodlawn

The typical new construction permit issued in Woodlawn took 37 days. The 75th-percentile wait was 92 days.

Records checked2572021–Sep. 15, 2026

The short answer

Typical wait37 daysmedian issued permit
Usually within92 days75% of records
Long-wait edge207 days90% of records
Evidence257issued permits

The median was 10 days faster than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
20.6%
1–7 days
9.7%
8–30 days
16.0%
31–90 days
28.4%
91+ days
25.3%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
20216122 days83 days210 days
2022496 days61 days128 days
20233936 days94 days222 days
20243642 days82 days189 days
20254774 days129 days291 days
2026*2549 days109 days149 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

New Construction timing in comparable community areas

ReportMedian75% withinRecords
Woodlawn37 days92 days257
Auburn Gresham36 days79 days29
Edison Park38 days85 days37
Greater Grand Crossing36 days91 days36
North Center38 days84 days373
Ohare38 days116 days31
Brighton Park42 days86 days77
Logan Square42 days112 days310