Community area × permit type
New Construction permits in Logan Square
The typical new construction permit issued in Logan Square took 42 days. The 75th-percentile wait was 112 days.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For New Construction permits in Logan Square, 310 issued permit records show a median processing time of 42 days; 75% were issued within 112 days and 90% within 230 days, covering January 2021 through September 15, 2026.
The median was 8.5 days faster than the previous 12 months.
New Construction permits in Logan Square: wait distribution
For New Construction permits in Logan Square, 310 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
New Construction permits in Logan Square: annual permit timing
New Construction permits in Logan Square has 6 publishable issue-year cohorts spanning 2021–2026, representing 310 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 73 | 0 days | 103 days | 200 days |
| 2022 | 56 | 0 days | 67 days | 147 days |
| 2023 | 42 | 26 days | 103 days | 212 days |
| 2024 | 45 | 60 days | 145 days | 221 days |
| 2025 | 53 | 56 days | 126 days | 261 days |
| 2026* | 41 | 68 days | 146 days | 360 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
New Construction permits in Logan Square: New Construction timing in comparable community areas
New Construction permits in Logan Square has 310 issued records, a 42 days median, and a 112 days 75th-percentile wait in this release.
| Report | Median | 75% within | Records |
|---|---|---|---|
| Brighton Park | 42 days | 86 days | 77 |
| Logan Square | 42 days | 112 days | 310 |
| Lower West Side | 43 days | 145 days | 173 |
| East Garfield Park | 44 days | 88 days | 162 |
| Edison Park | 38 days | 85 days | 37 |
| Jefferson Park | 46 days | 71 days | 78 |
| North Center | 38 days | 84 days | 373 |
| Ohare | 38 days | 116 days | 31 |
More New Construction permits in Logan Square comparisons
The New Construction permits in Logan Square cohort contains 310 issued records; related links retain separate location and permit-category cohorts.
All Logan Square permits Area reportNew Construction citywide Type report