Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

New Construction permits in Hyde Park

The typical new construction permit issued in Hyde Park took 1 day. The 75th-percentile wait was 5.2 days.

Records checked1202021–Sep. 15, 2026

The short answer

Typical wait1 daymedian issued permit
Usually within5.2 days75% of records
Long-wait edge28 days90% of records
Evidence120issued permits

Not enough records for a year-over-year comparison.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
44.2%
1–7 days
31.7%
8–30 days
14.2%
31–90 days
8.3%
91+ days
1.7%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
2021230 days1 day14 days
2022180 days0 days0 days
2023281 day12 days47 days
2024231 day5.5 days56 days
2025134 days19 days72 days
2026*153 days6 days12 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

New Construction timing in comparable community areas

ReportMedian75% withinRecords
Hyde Park1 day5.2 days120
Loop1 day7 days554
Near South Side1 day12 days251
North Park2 days70 days39
Armour Square3 days70 days80
Oakland5 days114 days25
Near North Side7 days48 days350
South Shore7.5 days126 days30