Official community area
Hyde Park permit processing times
For 2,256 issued permits in Hyde Park, the median processing time was 1 day; 75% were issued within 13 days.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Hyde Park permit processing times, 2,256 issued permit records show a median processing time of 1 day; 75% were issued within 13 days and 90% within 50 days, covering January 2021 through September 15, 2026.
The median was 1 day faster than the previous 12 months.
Hyde Park permit processing times: wait distribution
For Hyde Park permit processing times, 2,256 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Hyde Park permit processing times: annual permit timing
Hyde Park permit processing times has 6 publishable issue-year cohorts spanning 2021–2026, representing 2,256 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 416 | 0 days | 4.2 days | 24 days |
| 2022 | 416 | 0 days | 3 days | 27 days |
| 2023 | 455 | 1 day | 9 days | 48 days |
| 2024 | 381 | 4 days | 22 days | 70 days |
| 2025 | 326 | 7 days | 29 days | 64 days |
| 2026* | 262 | 5 days | 17 days | 56 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Hyde Park permit processing times: Nearby points in the citywide timing distribution
Hyde Park permit processing times has 2,256 issued records, a 1 day median, and a 13 days 75th-percentile wait in this release.
| Report | Median | 75% within | Records |
|---|---|---|---|
| Albany Park | 1 day | 14 days | 2,213 |
| Archer Heights | 1 day | 14 days | 812 |
| Ashburn | 1 day | 10 days | 2,411 |
| Auburn Gresham | 1 day | 11 days | 3,290 |
| Austin | 1 day | 14 days | 5,647 |
| Belmont Cragin | 1 day | 13 days | 2,724 |
| Beverly | 1 day | 13 days | 1,644 |
| Burnside | 1 day | 9.5 days | 227 |
More Hyde Park permit processing times comparisons
The Hyde Park permit processing times cohort contains 2,256 issued records; related links retain separate location and permit-category cohorts.
Express Permit Program 1 dayRenovation & Alteration 20 daysEasy Permit Process 0 daysSigns 20 daysNew Construction 1 dayElevator Equipment 0 days