Official community area

Beverly permit processing times

For 1,644 issued permits in Beverly, the median processing time was 1 day; 75% were issued within 13 days.

Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026

Records checked1,6442021–Sep. 15, 2026

The short answer

For Beverly permit processing times, 1,644 issued permit records show a median processing time of 1 day; 75% were issued within 13 days and 90% within 67 days, covering January 2021 through September 15, 2026.

Typical wait1 daymedian issued permit
Usually within13 days75% of records
Long-wait edge67 days90% of records
Evidence1,644issued permits

The median was 2 days slower than the previous 12 months.

Beverly permit processing times: wait distribution

For Beverly permit processing times, 1,644 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.

Same day
48.4%
1–7 days
20.1%
8–30 days
15.4%
31–90 days
8.9%
91+ days
7.2%

Change over time

Beverly permit processing times: annual permit timing

Beverly permit processing times has 6 publishable issue-year cohorts spanning 2021–2026, representing 1,644 issued records in the annual table.

Issue yearRecordsMedian75th percentile90th percentile
20213100 days7 days31 days
20223070 days11 days39 days
20233100 days13 days72 days
20242831 day20 days63 days
20252335 days31 days84 days
2026*2015 days15 days81 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Beverly permit processing times: Nearby points in the citywide timing distribution

Beverly permit processing times has 1,644 issued records, a 1 day median, and a 13 days 75th-percentile wait in this release.

ReportMedian75% withinRecords
Albany Park1 day14 days2,213
Archer Heights1 day14 days812
Ashburn1 day10 days2,411
Auburn Gresham1 day11 days3,290
Austin1 day14 days5,647
Belmont Cragin1 day13 days2,724
Beverly1 day13 days1,644
Burnside1 day9.5 days227