Renovation & Alteration permits in Beverly

The typical renovation & alteration permit issued in Beverly took 36 days. The 75th-percentile wait was 91 days.

Records checked3082021–Sep. 15, 2026

The short answer

Typical wait36 daysmedian issued permit
Usually within91 days75% of records
Long-wait edge179 days90% of records
Evidence308issued permits

The median was 10 days slower than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
22.1%
1–7 days
9.4%
8–30 days
13.3%
31–90 days
29.9%
91+ days
25.3%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
2021731 day34 days80 days
20227614 days40 days108 days
20234842 days80 days149 days
20244181 days150 days314 days
20254483 days147 days209 days
2026*26101 days164 days250 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Renovation & Alteration timing in comparable community areas

ReportMedian75% withinRecords
Beverly36 days91 days308
Austin35 days97 days1,097
Calumet Heights36 days86 days133
Englewood35 days97 days571
Logan Square36 days100 days1,286
Pullman35 days120 days99
South Deering36 days113 days85
West Pullman35 days96 days192