Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

Renovation & Alteration permits in Austin

The typical renovation & alteration permit issued in Austin took 35 days. The 75th-percentile wait was 97 days.

Records checked1,0972021–Sep. 15, 2026

The short answer

Typical wait35 daysmedian issued permit
Usually within97 days75% of records
Long-wait edge202 days90% of records
Evidence1,097issued permits

The median was 20 days slower than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
16.9%
1–7 days
14.6%
8–30 days
16.0%
31–90 days
25.1%
91+ days
27.4%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
202123212 days78 days211 days
20222437 days62 days136 days
202317920 days84 days205 days
202419844 days104 days198 days
202514764 days144 days287 days
2026*9870 days122 days191 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Renovation & Alteration timing in comparable community areas

ReportMedian75% withinRecords
Austin35 days97 days1,097
Englewood35 days97 days571
Pullman35 days120 days99
West Pullman35 days96 days192
Beverly36 days91 days308
Calumet Heights36 days86 days133
East Garfield Park34 days94 days400
Logan Square36 days100 days1,286